公司動態(tài) | 260000/220kV 變壓器生產(chǎn)進度更新
——Corporate Update | 260000/220kV Transformers Production Progress
發(fā)布時間:2025-03-31 15:51:32 人氣:805
經(jīng)過數(shù)周的生產(chǎn),公司承接的兩臺 260000/220kV 超高壓變壓器 生產(chǎn)正在穩(wěn)步推進,各項工藝嚴格按照計劃執(zhí)行,生產(chǎn)進度取得重要進展。
第 1 臺變壓器 已完成 吊罩檢查,所有內(nèi)部組件檢驗合格后,順利完成 蓋罩工序,進入后續(xù)工藝階段。
第 2 臺變壓器 已完成 器身整形,整體結(jié)構(gòu)調(diào)整達到設(shè)計標準,并 回爐處理,以確保絕緣系統(tǒng)的穩(wěn)定性。按照生產(chǎn)計劃,該變壓器將于 明日進入總裝并進行注油作業(yè)。
我們將繼續(xù)秉持 質(zhì)量第一、精益求精 的理念,嚴格把控每一道工藝環(huán)節(jié),確保變壓器產(chǎn)品的安全性和可靠性,按時高質(zhì)量交付客戶。
Today, the production of the two 260000/220kV ultra-high voltage transformers undertaken by our company has progressed steadily, with all processes executed according to plan and significant milestones achieved.
The first transformer has successfully completed the lifting cover inspection. After all internal components passed rigorous quality checks, the cover was reinstalled, marking the transition to the next production stage.
The second transformer has completed core structure shaping, with all mechanical adjustments meeting design standards. It has now been returned to the oven for further processing, ensuring the stability of its insulation system. According to the production schedule, final assembly and oil filling will take place tomorrow.
We remain committed to our philosophy of quality first and continuous improvement, strictly controlling every production step to ensure the safety and reliability of our transformers, and delivering high-quality products on schedule.